Energy projects / Germany / Niedersachsen
Biomass projects in Niedersachsen, Germany
276 biomass projects of 1 MW and up in Niedersachsen, Germany: 49 in the pipeline (112 MW planned, consented or under construction) and 212 in operation (455 MW). Source: Arcadium Data, data as of .
Use it through the API License the full dataset
Projects by stage
| Stage | Projects | Capacity |
|---|---|---|
| Planned (scoping or in planning) | 49 | 112 MW |
| In operation | 212 | 455 MW |
| Temporarily shut down | 10 | 19 MW |
| Decommissioned | 5 | 26 MW |
Largest projects in the pipeline
| Project | Technology | Stage | Capacity | Expected | Where | Operating company |
|---|---|---|---|---|---|---|
| Biomass project | Biomass | Planned (scoping or in planning) | 5 MW | 2023-01-02 | Börger, Niedersachsen | Sievers Wärme GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 5 MW | 2023-01-02 | Börger, Niedersachsen | Sievers Wärme GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 4 MW | 2029-05-31 | Loxstedt, Niedersachsen | |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2026-11-01 | Helvesiek, Niedersachsen | Bio-Energie Lauenbrück GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2022-12-31 | Papenburg, Niedersachsen | LCF Grüne Energie 2 GmbH & Co KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2022-12-31 | Papenburg, Niedersachsen | LCF Grüne Energie 2 GmbH & Co KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2022-12-31 | Papenburg, Niedersachsen | LCF Grüne Energie 3 GmbH & Co KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-04-01 | Ihlow, Niedersachsen | Agrarenergie Ihlowerfehn GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-04-01 | Ihlow, Niedersachsen | Agrarenergie Ihlowerfehn GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2027-07-01 | Alfhausen, Niedersachsen | |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2029-07-01 | Wietzen, Niedersachsen | Naturgas Wietzen GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-01-01 | Alfhausen, Niedersachsen | Rasche & Weßler GmbH |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-12-01 | Ganderkesee, Niedersachsen | A & C Naturenergie UG (haftungsbeschränkt) & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2027-07-01 | Berge, Niedersachsen | EfB Energie für Berge GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2027-07-01 | Alfhausen, Niedersachsen | |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2027-07-01 | Berge, Niedersachsen | EfB Energie für Berge GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2026-10-12 | Dötlingen, Niedersachsen | Krim Energiegewinnungs GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-01-01 | Alfhausen, Niedersachsen | Rasche & Weßler GmbH |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-12-01 | Ganderkesee, Niedersachsen | A & C Naturenergie UG (haftungsbeschränkt) & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-01-01 | Badbergen, Niedersachsen | Budke Milch GmbH & Co.KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-01-01 | Großenkneten, Niedersachsen | Heinefelder Biogas GmbH & Co.KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2028-04-01 | Ostereistedt, Niedersachsen | MPO Biogas GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 3 MW | 2029-01-01 | Hankensbüttel, Niedersachsen | AGIL Bioenergie GmbH & Co. KG |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2026-09-01 | Alfhausen, Niedersachsen | |
| Biomass project | Biomass | Planned (scoping or in planning) | 2 MW | 2026-09-01 | Alfhausen, Niedersachsen |
Operating companies
| Operating company | Projects | Capacity |
|---|---|---|
| BEH Bioenergie Hannover GmbH | 10 | 40 MW |
| Statkraft Markets GmbH | 2 | 40 MW |
| EBE Holzheizkraftwerk GmbH | 1 | 21 MW |
| FORTE Energie GmbH & Co. KG | 1 | 17 MW |
| Biomethan Produktion Ottersberg GmbH | 7 | 11 MW |
| BEKW Bioenergiekraftwerk Emsland GmbH & Co. KG | 1 | 11 MW |
| Energiezentrale 4.0 Bersenbrück GmbH | 2 | 9 MW |
| Sievers Wärme GmbH & Co. KG | 2 | 9 MW |
| DBE-Dollbergen Bioenergie GmbH | 1 | 9 MW |
| BALANCE Erneuerbare Energien GmbH | 6 | 8 MW |
| EBE - Elsflether Bioenergie GmbH | 1 | 7 MW |
| Rasche & Weßler GmbH | 3 | 7 MW |
| LCF Grüne Energie 2 GmbH & Co KG | 2 | 7 MW |
| Pfeifer Holz GmbH Uelzen | 1 | 7 MW |
| Ebersdorfer Biostrom GmbH | 5 | 6 MW |
| Heeseberg Biogas GmbH & Co.KG | 3 | 6 MW |
| Biogas Ahe GmbH | 3 | 6 MW |
| Agrarenergie Ihlowerfehn GmbH & Co. KG | 2 | 5 MW |
| Braunschweiger Versorgungs-AG & Co. KG | 3 | 5 MW |
| A & C Naturenergie UG (haftungsbeschränkt) & Co. KG | 2 | 5 MW |
| EfB Energie für Berge GmbH & Co. KG | 2 | 5 MW |
| GETEC BBE GmbH | 1 | 5 MW |
| Ricon GmbH & Co. KG | 1 | 5 MW |
| Fürstenauer Wärme GmbH | 2 | 5 MW |
| Zeus Renewables GmbH | 3 | 4 MW |
Projects of 1 MW and up. Capacity is net nominal capacity (Germany) or the total capacity of the queue entry (Great Britain). A hybrid project counts under each technology it lists. Companies only: private persons are never shown as operators, and no coordinates or street addresses are published. Data as of 2026-10-25, updated monthly.
Germany: Marktstammdatenregister, Bundesnetzagentur, Datenlizenz Deutschland - Namensnennung - Version 2.0 (www.govdata.de/dl-de/by-2-0). Great Britain: Supported by National Energy SO Open Data (NESO Open Data Licence, TEC register and Embedded register).
Questions
Where does this data come from?
Germany: the public Marktstammdatenregister of the Bundesnetzagentur, including units in planning. We load the official files, keep projects of 1 MW and up and record changes between loads.
Does the list show private owners?
No. Operators are shown only when they are companies. Private persons, sole traders and names that could belong to a person are left out, and the data holds no coordinates or street addresses.
How often is it updated?
Monthly. Each load records new projects, changes of stage, capacity or connection date, and projects that left the register.
Cite as: Arcadium Data, "Biomass projects in Niedersachsen, Germany: 49 in the pipeline, 112 MW", https://arcadiumdata.io/energy/de/niedersachsen/biomass/, data as of 2026-10-25.