Energy projects / Germany / Sachsen-Anhalt

Battery and other storage projects in Sachsen-Anhalt, Germany

69 battery and other storage projects of 1 MW and up in Sachsen-Anhalt, Germany: 33 in the pipeline (637 MW planned, consented or under construction) and 35 in operation (612 MW). Source: Arcadium Data, data as of .

Use it through the API License the full dataset

Projects by stage

StageProjectsCapacity
Planned (scoping or in planning)33637 MW
In operation35612 MW
Decommissioned11 MW

Largest projects in the pipeline

ProjectTechnologyStageCapacityExpectedWhereOperating company
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)300 MW2027-02-01Staßfurt, Sachsen-AnhaltECO POWER THREE GmbH
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)58 MW2026-10-31Magdeburg, Sachsen-AnhaltKyon-42 Battery Storage GmbH
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)30 MW2026-09-30Hohenberg-Krusemark, Sachsen-AnhaltNEOEN Speicher 1
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)24 MW2026-12-31Angern, Sachsen-AnhaltPV Lako Angern GmbH & Co. KG
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)24 MW2026-10-08Sülzetal, Sachsen-AnhaltKyon-26 Battery Storage GmbH
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)20 MW2026-11-28Arneburg, Sachsen-Anhalt
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)15 MW2027-01-01Klötze, Sachsen-AnhaltKunrau Instant Power GmbH & Co. KG
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)15 MW2026-09-23Bernburg (Saale), Sachsen-AnhaltAxpo Storage DE 2 GmbH & Co. KG
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)15 MW2027-01-15Harzgerode, Sachsen-AnhaltTauber Energy Storage 7 GmbH
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)13 MW2026-10-30Sandersdorf-Brehna, Sachsen-AnhaltISM Bitterfeld GmbH
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)12 MW2025-10-15Hettstedt, Sachsen-AnhaltBESS Hettstedt Fünfte Energie GmbH
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)12 MW2026-06-30Weißenfels, Sachsen-AnhaltKlaron Neunte Energie GmbH
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)10 MW2027-01-01Osternienburger Land, Sachsen-AnhaltInfrastrukturgesellschaft Reppichau mbH & Co.KG
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)8 MW2027-02-01Gardelegen, Sachsen-AnhaltRP Deutschland 1 GmbH
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)7 MW2027-07-01Klötze, Sachsen-AnhaltTEP Irene GmbH & Co. KG
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)7 MW2027-07-01Tangerhütte, Sachsen-AnhaltTEP Eunomia GmbH & Co. KG
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)7 MW2028-02-01Zörbig, Sachsen-AnhaltSolarpark Rieda GmbH & Co. KG
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)7 MW2027-07-01Zörbig, Sachsen-AnhaltEB Solar GmbH & Co. KG
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)7 MW2027-08-25Braunsbedra, Sachsen-AnhaltSonnenquelle Geiseltal GmbH & Co. KG
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)7 MW2027-03-26Braunsbedra, Sachsen-AnhaltSonnenquelle Geiseltal GmbH & Co. KG
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)6 MW2027-03-30Calvörde, Sachsen-AnhaltSomikon Zukunftsenergie 8 GmbH & Co. KG
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)5 MW2027-05-31Teutschenthal, Sachsen-AnhaltENERPARC Solar Invest 230 TU 35 GmbH & Co. KG
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)5 MW2026-12-19Tangermünde, Sachsen-Anhalt
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)4 MW2026-08-01Elbe-Parey, Sachsen-AnhaltMando Multiwerke Nr. 20
Battery and other storage projectBattery and other storagePlanned (scoping or in planning)3 MW2026-08-01Möckern, Sachsen-AnhaltMando Multiwerke Nr. 7

Operating companies

Operating companyProjectsCapacity
ECO POWER THREE GmbH1300 MW
Seerose Energie GmbH1105 MW
Kyon-42 Battery Storage GmbH282 MW
Vattenfall Wasserkraft GmbH280 MW
Münch EnerStore GmbH146 MW
Münch NatureDepot GmbH146 MW
Münch NextGen Storage GmbH146 MW
Münch SmartCharge Systems GmbH146 MW
Münch VoltDepot GmbH146 MW
NEOEN Speicher 1130 MW
PV Lako Angern GmbH & Co. KG124 MW
SMAREG 8 GmbH & Co. KG121 MW
BSA Elsteraue GmbH120 MW
Solar Zerbst GmbH & Co.KG118 MW
ISM Bitterfeld GmbH218 MW
Obton Tangermünde GmbH & Co. KG116 MW
Axpo Storage DE 2 GmbH & Co. KG115 MW
Kunrau Instant Power GmbH & Co. KG115 MW
Tauber Energy Storage 7 GmbH115 MW
BESS Oberröblingen GmbH & Co. KG114 MW
BESS Quedlinburg GmbH & Co. KG114 MW
Obton Storage GmbH & Co. KG114 MW
Sonnenquelle Geiseltal GmbH & Co. KG213 MW
BEE Merseburg GmbH112 MW
BESS Hettstedt Fünfte Energie GmbH112 MW

Projects of 1 MW and up. Capacity is net nominal capacity (Germany) or the total capacity of the queue entry (Great Britain). A hybrid project counts under each technology it lists. Companies only: private persons are never shown as operators, and no coordinates or street addresses are published. Data as of 2026-10-25, updated monthly.

Germany: Marktstammdatenregister, Bundesnetzagentur, Datenlizenz Deutschland - Namensnennung - Version 2.0 (www.govdata.de/dl-de/by-2-0). Great Britain: Supported by National Energy SO Open Data (NESO Open Data Licence, TEC register and Embedded register).

Questions

Where does this data come from?

Germany: the public Marktstammdatenregister of the Bundesnetzagentur, including units in planning. We load the official files, keep projects of 1 MW and up and record changes between loads.

Does the list show private owners?

No. Operators are shown only when they are companies. Private persons, sole traders and names that could belong to a person are left out, and the data holds no coordinates or street addresses.

How often is it updated?

Monthly. Each load records new projects, changes of stage, capacity or connection date, and projects that left the register.

Cite as: Arcadium Data, "Battery and other storage projects in Sachsen-Anhalt, Germany: 33 in the pipeline, 637 MW", https://arcadiumdata.io/energy/de/sachsen-anhalt/storage/, data as of 2026-10-25.